ADDITIONAL 100 MLD W.S.SCHEME FOR THANE MUNICIPAL CORPORATION

 

1.

Date of Administrative Approval

2.3.1998

2.

Date of start

10/1998

3.

Sanctioned Cost

Rs.121.42 Crores

4.

Date of Commissioning

APRIL 2001

5.

Completion Cost of the Project

Expdt. upto 31.12.2002 Rs.

6.

Supply in LPCD before commissioning

203 LPCD

7.

Supply in LPCD after commissioning

251 LPCD

8.

Description of Sub work in short :-

 


i)                     Approach Channel having RCC Pipe of 1400mm dia in 2 rows.

ii)                   Sump and Pump House. Sump size 16m x 10m x 10m, Pump House size 16mx10mx18m

iii)                  600 HP 4 Nos. Raw Water Pumping Machinery at Pise Head Works.

iv)                  Bridge on Bhasta River 7.00 m wide.

v)                    1244 mm dia M.S. Raw Water Rising Main from Pise Head works to BPT at Sonale L=10.41 Km.

vi)                  B.P.T.having capacity 0.64 MLD

vii)                 1044 mm dia P.S.C. Raw Water Gravity Main from Sonale BPT to WTP at Temghar L=5.88 Km.

viii)               Water Treatment Plant Capacity 140 MLD at Temghar.

ix)                 900 HP 4 Nos. Pure Water Pumping Machinery at Temghar.

x)                   2052 mm dia M.S. Pure Water Gravity Main from Temghar WTP to Mankoli MBR L=3.6 Km.

xi)                 2044 mm dia M.S. Pure Water Gravity Main from Mankoli MBR to Majiwada. L = 5.0 Km.

xii)                Repairing to existing Anjur Bridge L= 1.30 Km.,

xiii)              Brige on Kalwa Creek near Saket.11 m wide L = 365 m.

9.

Beneficiaries

Thane Municipal Corporation, having population 12,62,000 Souls.